Land Off Folly Lane is operational in East Lindsey with a recorded capacity of 5 MW, and has been generating since 2016-03-07.
Planning and build timeline
| Application submitted | 2015-06-18 |
| Permission granted | 2015-09-17 3 months after submission |
| Operational | 2016-03-07 6 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Lindsey’s record on solar
East Lindsey has decided 28 solar farms and approved 100%, taking a median of 3 months. See every solar farm decision in East Lindsey →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Carrington Farm AD Anaerobic Digestion · Operational | 3 | 4.5 km |
Staples Anaerobic Digestion CHP Plant (Waste AD) Anaerobic Digestion · Operational | 1.4 | 8.7 km |
Grange Farm (Kirkby on Bain) Solar Photovoltaics · Operational | 9 | 10.3 km |
Canopus Farm Solar Photovoltaics · Operational | 5 | 11 km |
Leverton Ings Solar Photovoltaics · Operational | 12 | 11.1 km |
Low Farm Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 13.5 km |
Marsh Farm (Farm AD) Anaerobic Digestion · Operational | 1.4 | 14.3 km |
Bicker Fen (previously Manor Farm) Solar Photovoltaics · Operational | 22.6 | 14.9 km |
How big is Land Off Folly Lane?
Land Off Folly Lane has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land Off Folly Lane?
REPD records the operator as Solar Century/ Bluefield Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land Off Folly Lane approved and built?
The application was submitted on 2015-06-18. Permission was granted on 2015-09-17, 3 months later. The site became operational on 2016-03-07, 6 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5483.