Cold Harbour Farm

Cold Harbour Farm is an operational 5 MW solar farm in North Yorkshire, generating since 18 December 2015. Planning permission was granted on 18 February 2015, 4 months after submission. Operator of record: Lightsource Renewable Energy.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 18 December 2015
Solar Photovoltaics
Technology
Lightsource Renewable Energy
North Yorkshire
Authority
England

Planning and build timeline

Application submitted3 November 2014
Permission granted18 February 2015
4 months after submission
Operational18 December 2015
10 months after consent

Screening a site of your own?

RedlineUK · £39

North Yorkshire approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Cold Harbour Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Yorkshire’s record on solar

North Yorkshire has decided 105 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North Yorkshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
56 km
Solar Photovoltaics · Operational
34.76.4 km
Battery · Operational
276.4 km
Solar Photovoltaics · Operational
59.2 km
Solar Photovoltaics · Operational
511.8 km
Solar Photovoltaics · Operational
0.2412.5 km
Solar Photovoltaics · Under Construction
13.1 km

How big is Cold Harbour Farm?

Cold Harbour Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cold Harbour Farm?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cold Harbour Farm approved and built?

The application was submitted on 3 November 2014. Permission was granted on 18 February 2015, 4 months later. The site became operational on 18 December 2015, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4745.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode