Novarly ParcelRenewable sites

Renewable sitesLand at Oxcroft Stocking Ground

Land at Oxcroft Stocking Ground

Land at Oxcroft Stocking Ground is operational in Bolsover with a recorded capacity of 3 MW, and has been generating since 2016-03-20.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-20
Solar Photovoltaics
Technology
Anesco
Bolsover
Authority
England

Planning and build timeline

Application submitted2015-08-03
Permission granted2015-12-09
4 months after submission
Operational2016-03-20
3 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bolsover’s record on solar

Bolsover has decided 10 solar farms and approved 80%, taking a median of 2.9 months. See every solar farm decision in Bolsover

Other built sites within 15 km

SiteMWDistance
Oxcroft Solar Farm
Battery · Operational
10 km
Land at Oxcroft Stocking Ground
Solar Photovoltaics · Operational
41 km
Inkersall Road, Staveley - Solar Photovoltaic Farm And Battery Storage
Solar Photovoltaics · Operational
313 km
Inkersall Road, Staveley - Solar Photovoltaic Farm And Battery Storage
Battery · Operational
3 km
Land at Bolsover Moor Quarry
Solar Photovoltaics · Operational
53.3 km
Arkwright Solar Farm
Solar Photovoltaics · Operational
83.8 km
Cherry Tree Farm
Solar Photovoltaics · Operational
54.1 km
Staveley Power
Landfill Gas · Operational
2.14.9 km

How big is Land at Oxcroft Stocking Ground?

Land at Oxcroft Stocking Ground has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land at Oxcroft Stocking Ground?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land at Oxcroft Stocking Ground approved and built?

The application was submitted on 2015-08-03. Permission was granted on 2015-12-09, 4 months later. The site became operational on 2016-03-20, 3 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5591.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council