Renewable sites › Land Adjacent to Thomas Swan and Co Ltd.
Land Adjacent to Thomas Swan and Co Ltd.
Land Adjacent to Thomas Swan and Co Ltd. is operational in County Durham with a recorded capacity of 1 MW, and has been generating since 2014-12-15.
Planning and build timeline
| Application submitted | 2013-02-26 |
| Permission granted | 2013-07-03 4 months after submission |
| Operational | 2014-12-15 17 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Derwentside Environmental Testing Servs Limited - Solar pv panels Solar Photovoltaics · Operational | 0.38 | 2 km |
Hownsgill Industrial Park Solar Photovoltaics · Under Construction | 5 | 2.5 km |
Greencroft Estate Turbines Wind Onshore · Operational | 4 | 4.3 km |
Green Croft Solar Farm Solar Photovoltaics · Operational | 5 | 5.1 km |
Chapman's Well Landfill Gas · Operational | 1 | 5.3 km |
Kiln Pit Hill Windfarm Wind Onshore · Operational | 12 | 7.3 km |
Boundary Lane Wind Onshore · Operational | 6 | 7.4 km |
Holmside Hall Wind Onshore · Operational | 2.8 | 8.8 km |
How big is Land Adjacent to Thomas Swan and Co Ltd.?
Land Adjacent to Thomas Swan and Co Ltd. has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land Adjacent to Thomas Swan and Co Ltd.?
REPD records the operator as Hallwick Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land Adjacent to Thomas Swan and Co Ltd. approved and built?
The application was submitted on 2013-02-26. Permission was granted on 2013-07-03, 4 months later. The site became operational on 2014-12-15, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 349.
Novarly Parcel · official public data, read properly · parcel.novarly.com