Kiln Pit Hill Windfarm

Kiln Pit Hill Windfarm is operational in Northumberland with a recorded capacity of 12 MW, and has been generating since 2012-08-01.

12 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-08-01
Wind Onshore
Technology
Npower Renewables
Northumberland
Authority
England

Planning and build timeline

Application submitted2006-02-15
Permission granted2009-01-02
35 months after submission
Operational2012-08-01
43 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Northumberland’s record on onshore wind

Northumberland has decided 31 onshore wind schemes and approved 52%, taking a median of 16.3 months. See every onshore wind scheme decision in Northumberland

Other built sites within 15 km

SiteMWDistance
Boundary Lane
Wind Onshore · Operational
64.3 km
Derwentside Environmental Testing Servs Limited - Solar pv panels
Solar Photovoltaics · Operational
0.385.6 km
Hownsgill Industrial Park
Solar Photovoltaics · Under Construction
57 km
Land Adjacent to Thomas Swan and Co Ltd.
Anaerobic Digestion · Operational
17.3 km
Greencroft Estate Turbines
Wind Onshore · Operational
411.4 km
Green Croft Solar Farm
Solar Photovoltaics · Operational
512.2 km
Chapman's Well
Landfill Gas · Operational
112.3 km
Burnhills Landfill Scheme (L4)
Landfill Gas · Operational
1.512.7 km

How big is Kiln Pit Hill Windfarm?

Kiln Pit Hill Windfarm has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Kiln Pit Hill Windfarm?

REPD records the operator as Npower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Kiln Pit Hill Windfarm approved and built?

The application was submitted on 2006-02-15. Permission was granted on 2009-01-02, 35 months later. The site became operational on 2012-08-01, 43 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3938.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council