Kinegar Quarry

Kinegar Quarry is an operational 5 MW onshore wind farm in Scottish Borders, generating since 15 March 2017. Planning permission was granted on 21 March 2013, 13 months after submission. Operator of record: Airvolution Energy.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 15 March 2017
Wind Onshore
Technology
Airvolution Energy
Scottish Borders
Authority
Scotland

Planning and build timeline

Application submitted20 February 2012
Permission granted21 March 2013
13 months after submission
Operational15 March 2017
48 months after consent

Screening a site of your own?

RedlineUK · £39

Scottish Borders approves 56% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Kinegar Quarry’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Borders’s record on onshore wind

Scottish Borders has decided 41 onshore wind schemes and approved 56%, taking a median of 13.6 months. See every onshore wind scheme decision in Scottish Borders

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
6.92.3 km
Wind Onshore · Operational
1.54 km
Wind Onshore · Operational
28.75 km
Wind Onshore · Under Construction
166.6 km
Landfill Gas · Operational
2.27.2 km
Wind Onshore · Operational
81.77.2 km
Landfill Gas · Operational
147.5 km
Wind Onshore · Operational
29.97.5 km

How big is Kinegar Quarry?

Kinegar Quarry has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Kinegar Quarry?

REPD records the operator as Airvolution Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Kinegar Quarry approved and built?

The application was submitted on 20 February 2012. Permission was granted on 21 March 2013, 13 months later. The site became operational on 15 March 2017, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4601.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode