Kinegar Quarry
Kinegar Quarry is an operational 5 MW onshore wind farm in Scottish Borders, generating since 15 March 2017. Planning permission was granted on 21 March 2013, 13 months after submission. Operator of record: Airvolution Energy.
Planning and build timeline
| Application submitted | 20 February 2012 |
| Permission granted | 21 March 2013 13 months after submission |
| Operational | 15 March 2017 48 months after consent |
Screening a site of your own?
Scottish Borders approves 56% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Kinegar Quarry’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Borders’s record on onshore wind
Scottish Borders has decided 41 onshore wind schemes and approved 56%, taking a median of 13.6 months. See every onshore wind scheme decision in Scottish Borders →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 6.9 | 2.3 km |
Wind Onshore · Operational | 1.5 | 4 km |
Wind Onshore · Operational | 28.7 | 5 km |
Wind Onshore · Under Construction | 16 | 6.6 km |
Landfill Gas · Operational | 2.2 | 7.2 km |
Wind Onshore · Operational | 81.7 | 7.2 km |
Landfill Gas · Operational | 14 | 7.5 km |
Wind Onshore · Operational | 29.9 | 7.5 km |
How big is Kinegar Quarry?
Kinegar Quarry has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kinegar Quarry?
REPD records the operator as Airvolution Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kinegar Quarry approved and built?
The application was submitted on 20 February 2012. Permission was granted on 21 March 2013, 13 months later. The site became operational on 15 March 2017, 48 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4601.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode