Renewable planning › Onshore wind › Scottish Borders
Onshore wind planning in Scottish Borders
Scottish Borders has decided 41 onshore wind schemes and approved 56% of them, taking a median of 13.6 months to decide. Consented capacity: 432 MW. 7 applications still awaiting a decision.
How Scottish Borders compares
Against the 75 UK authorities with 5+ onshore wind decisions, Scottish Borders sits in the 24th percentile for approval rate (12 points below the England average) and the 55th percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (56)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Pressmains, Coldingham - Wind Turbine J Dalton & Sons · 25/00650/FUL · 3.7 mo to decide | 0.2 | Awaiting Construction | 2025-09-12 |
Monashee Farm, Drakemyre - Wind Turbines GSC Monashee Farm Limited · 25/00473/FUL | 24 | Application Submitted | 2025-04-17 |
Monashee Wind Farm Green Switch Capital Limited · 25/00473/FUL | 24 | Application Submitted | 2025-04-17 |
Wull Muir Wind Farm Energiekontor UK Limited · 22/01960/FUL · 18.7 mo to decide | 36 | Application Refused | 2024-07-08 |
Blackburn Mill Farm, Grantshouse - Wind Turbines Wind Estate (UK) Ltd · 23/00996/FUL · 9 mo to decide | 16.8 | Awaiting Construction | 2024-04-19 |
Ayton Mains Farmhouse - Wind Turbines Constantine Group Limited · 23/01904/FUL | 0.16 | Application Withdrawn | 2024-03-15 |
Wull Muir Wind Farm EnergieKontor UK · 19/00191/FUL · 10.2 mo to decide | 33.6 | Revised | 2020-02-05 |
Barrel Law Wind Farm Barrel Law Windfarm · 17/01255/FUL · 11.8 mo to decide | 24.5 | Appeal Refused | 2018-09-03 |
Pines Burn Wind Farm EnergieKontor UK · 17/00010/FUL · 19.2 mo to decide | 33.6 | Operational | 2018-08-17 |
Howpark Wind Farm Eurowind (UK) Limited · 16/00980/FUL · 20 mo to decide | 16 | Under Construction | 2018-04-24 |
Highlee Hill Wind Farm Renewable Energy Systems (RES) · 16/00810/FUL | 44.9 | Application Withdrawn | 2017-05-11 |
Longpark Wind Farm Extension Wind Prospect · 14/00417/S36 | 14 | Application Withdrawn | 2017-03-16 |
Gilston Hill Wind Farm 2020 Renewables/ Forsa Energy · 17/00226/FUL | 21 | Appeal Refused | 2017-02-01 |
Windy Edge Wind Farm Energiekontor · 13/00789/FUL · 35.2 mo to decide | 27 | Planning Permission Expired | 2016-06-09 |
Cummings Hill Wind Farm Infinis/Cummings Hill Wind Farm Ltd · 14/00083/FUL | 21 | Application Withdrawn | 2015-09-28 |
Glenkerie Wind Farm Extension Muirhall Energy (formerly Infinis) · 13/00552/FUL · 26.5 mo to decide | 15 | Planning Permission Expired | 2015-07-29 |
Kilrubie Wind Farm Kilrubie Wind Farm · 15/00818/FUL | 21 | Appeal Withdrawn | 2015-07-14 |
Muircleugh Farm Airvolution Energy · 14/01081/FUL · 5.9 mo to decide | 21 | Appeal Refused | 2015-03-31 |
Hag Law Stevenson Hill Wind Energy · 14/00738/FUL · 6.9 mo to decide | 20 | Appeal Refused | 2015-02-03 |
Hoprigshiels Community Wind Farm Private Developer · 11/00664/FUL · 41.5 mo to decide | 6.9 | Operational | 2014-11-20 |
Moorhouse Farm Urban Wind · 13/00615/FUL · 14.8 mo to decide | 1 | Operational | 2014-09-11 |
Muircleugh Farm Airvolution Energy · 13/00044/FUL | 12 | Revised | 2013-10-24 |
Penmanshiel Wind Farm Renewable Energy Systems (RES) · 11/01464/FUL · 23.7 mo to decide | 28.7 | Operational | 2013-10-16 |
Shaw Park Wind Farm J G Shanks & Son Ltd · 11/01175/FUL · 25.3 mo to decide | 20.7 | Appeal Refused | 2013-10-08 |
Blinkbonny Private Developer · 13/00561/FUL | 4.6 | Application Withdrawn | 2013-09-09 |
HORN BURN WIND FARM - WIND TURBINES Energiekontor UK · 12/01348/FUL · 10 mo to decide | 20 | Appeal Refused | 2013-08-29 |
Brunta Hill Wind Farm PNE Wind UK Ltd (Brookfield) · 11/01444/FUL · 21.5 mo to decide | 18.4 | Appeal Refused | 2013-08-05 |
Whitton Farm Vattenfall · 09/01162/FUL · 46.4 mo to decide | 15 | Application Refused | 2013-07-08 |
Monashee Wind Farm Element Power · 12/00431/FUL | 15 | Application Withdrawn | 2013-06-25 |
Quixwood Moor NTR PLC · 11/01662/FUL · 15.3 mo to decide | 29.9 | Operational | 2013-04-02 |
Kinegar Quarry Airvolution Energy · 12/00221/FUL · 13 mo to decide | 5 | Operational | 2013-03-21 |
Barrel Law Wind Farm ABO Wind · 12/00191/FUL · 12.6 mo to decide | 24 | Appeal Refused | 2013-03-04 |
Corsbie Moor Wind Farm E.ON Climate & Renewables · 11/00888/FUL · 14.2 mo to decide | 27 | Appeal Refused | 2012-09-03 |
Blackburn Farm Volkswind UK Ltd · 11/01077/FUL · 12.2 mo to decide | 21 | Application Refused | 2012-08-06 |
Spurlens Rig Wind Cluster Lomond Energy · 10/01669/FUL · 11.8 mo to decide | 12 | Application Refused | 2011-11-30 |
Broadmeadows Green Power · 04/02501/FUL · 77.6 mo to decide | 36 | Appeal Refused | 2011-06-13 |
Keith Hill Sky Wind Energy · 10/00985/P · 4.5 mo to decide | 4.5 | Operational | 2011-04-01 |
Muircleugh Farm Airvolution Energy · 10/01641/FUL | 4 | Revised | 2011-02-17 |
Kinegar Quarry Wind Direct · 10/00364/FUL · 6.1 mo to decide | 5 | Revised | 2010-09-15 |
Minch Moor AMEC · 03/00627/FUL · 87.9 mo to decide | 21.6 | Application Refused | 2010-08-09 |
Brockholes Wind Cluster Brockholes Farm · 09/00516/FUL · 12.8 mo to decide | 2.4 | Operational | 2010-05-10 |
Glenkerie Wind Farm Novera Energy · 07/02478/FUL · 8.6 mo to decide | 22 | Operational | 2008-09-08 |
Drone Hill Greencoat UK Wind · 05/00425/FUL · 32.3 mo to decide | 28.6 | Operational | 2007-11-12 |
Dunion Hill Wind Farm WINDJEN POWER LTD · 05/02336/FUL · 19.5 mo to decide | 18.4 | Application Refused | 2007-09-11 |
Langhope Rig Greencoat UK Wind · 06/01236/FUL · 12.5 mo to decide | 16 | Operational | 2007-07-17 |
Carcant Windfarm Greencoat UK Wind · 05/01884/FUL · 11.2 mo to decide | 6 | Operational | 2006-09-15 |
Falahill E.ON UK · 04/02420/FUL · 16.9 mo to decide | 6.7 | Application Refused | 2006-05-08 |
Blinkbonny Heights Private Developer | 5 | Revised | 2006-04-27 |
Dun Law Extension Renewable Energy Systems (RES) · 8.7 mo to decide | 29.8 | Operational | 2006-01-16 |
Sell Moor Windfarm RDC Scotland Ltd · 04/00350/FUL · 18 mo to decide | 47.5 | Application Refused | 2005-08-31 |
Longpark Wind Prospect · 04/00317/FUL · 18.5 mo to decide | 38 | Operational | 2005-08-31 |
Toddleburn Scottish and Southern Energy (SSE) · 04/017744/FUL · 11.9 mo to decide | 27.6 | Operational | 2005-08-31 |
Monashee West Coast Windfarms Ltd · 02/01319FUL | 15 | Application Withdrawn | 2004-03-30 |
Black Hill (Borders) Renewable Energy Systems (RES) · 01/00058/FUL · 5.3 mo to decide | 28.6 | Operational | 2001-07-02 |
Bowbeat Emly Bank / Rough Side PowerGen and Natural Power · 00/00371/FUL · 4.7 mo to decide | 31.2 | Operational | 2000-08-14 |
Dun Law Renewable Energy Systems (RES) · 96/01130/FUL · 14.5 mo to decide | 17.2 | Operational | 1997-07-31 |
Does Scottish Borders approve onshore wind schemes?
Yes — of the 41 onshore wind schemes Scottish Borders has decided, 56% were approved (23 granted, 18 refused). The UK-wide rate for onshore wind is 68%.
How long does a onshore wind scheme application take in Scottish Borders?
The median time from application to decision is 13.6 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Scottish Borders consented?
432 MW has been consented across 23 approved schemes, with 411 MW refused. A further 7 applications awaits a decision.
Other technologies in Scottish Borders
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.