Novarly ParcelRenewable sites

Renewable sitesFerneylea Farm

Ferneylea Farm

Ferneylea Farm is an operational 1.5 MW onshore wind farm in East Lothian, generating since 1 January 2015. Planning permission was granted on 7 March 2012, 18 months after submission. Operator of record: CBK Galbraith.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 January 2015
Wind Onshore
Technology
CBK Galbraith
East Lothian
Authority
Scotland

Planning and build timeline

Application submitted21 September 2010
Permission granted7 March 2012
18 months after submission
Operational1 January 2015
34 months after consent

Screening a site of your own?

RedlineUK · £39

East Lothian approves 100% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ferneylea Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

East Lothian’s record on onshore wind

East Lothian has decided 5 onshore wind schemes and approved 100%, taking a median of 10.6 months. See every onshore wind scheme decision in East Lothian

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
6.91.8 km
Wind Onshore · Operational
81.73.2 km
Wind Onshore · Operational
54 km
Wind Onshore · Operational
60.84.5 km
Wind Onshore · Operational
484.5 km
Battery · Operational
806.1 km
Wind Onshore · Operational
28.76.4 km
Wind Onshore · Operational
62.56.6 km

How big is Ferneylea Farm?

Ferneylea Farm has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ferneylea Farm?

REPD records the operator as CBK Galbraith. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ferneylea Farm approved and built?

The application was submitted on 21 September 2010. Permission was granted on 7 March 2012, 18 months later. The site became operational on 1 January 2015, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6388.