Quixwood Moor
Quixwood Moor is an operational 29.9 MW onshore wind farm in Scottish Borders, generating since 9 March 2017. Planning permission was granted on 2 April 2013, 15 months after submission. Operator of record: NTR PLC.
Planning and build timeline
| Application submitted | 22 December 2011 |
| Permission granted | 2 April 2013 15 months after submission |
| Operational | 9 March 2017 47 months after consent |
Screening a site of your own?
Scottish Borders approves 56% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Quixwood Moor’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Borders’s record on onshore wind
Scottish Borders has decided 41 onshore wind schemes and approved 56%, taking a median of 13.6 months. See every onshore wind scheme decision in Scottish Borders →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 28.7 | 3.8 km |
Wind Onshore · Operational | 2.4 | 4.1 km |
Wind Onshore · Under Construction | 16 | 5.6 km |
Wind Onshore · Operational | 6.9 | 6.4 km |
Wind Onshore · Operational | 28.6 | 6.6 km |
Wind Onshore · Operational | 1.5 | 6.7 km |
Wind Onshore · Operational | 81.7 | 6.9 km |
Wind Onshore · Operational | 5 | 7.5 km |
How big is Quixwood Moor?
Quixwood Moor has a recorded installed capacity of 29.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Quixwood Moor?
REPD records the operator as NTR PLC. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Quixwood Moor approved and built?
The application was submitted on 22 December 2011. Permission was granted on 2 April 2013, 15 months later. The site became operational on 9 March 2017, 47 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4179.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode