Royal Oak Way South - Solar Array is operational in West Northamptonshire with a recorded capacity of 1.66 MW, and has been generating since 2023-10-01.

1.66 MW
Capacity
as recorded in REPD
Operational
Status
since 2023-10-01
Solar Photovoltaics
Technology
Cummins Limited
West Northamptonshire
Authority
England

Planning and build timeline

Application submitted2022-02-22
Permission granted2022-05-24
3 months after submission
Operational2023-10-01
16 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Northamptonshire’s record on solar

West Northamptonshire has decided 61 solar farms and approved 92%, taking a median of 2.9 months. See every solar farm decision in West Northamptonshire

Other built sites within 15 km

SiteMWDistance
Daventry
Biomass (dedicated) · Operational
10.9 km
Kilsby Landfill Scheme
Landfill Gas · Operational
16.5 km
Watford Lodge
Wind Onshore · Operational
12.58.6 km
M1 J18 Wind Turbines
Wind Onshore · Operational
49.8 km
East Haddon - Solar Photovoltaic System
Solar Photovoltaics · Under Construction
211 km
Crick Road
Solar Photovoltaics · Under Construction
49.911.2 km
Weston Landfill Site
Landfill Gas · Operational
211.6 km
Boddington Reservoir
Wind Onshore · Operational
1.512 km

How big is Royal Oak Way South - Solar Array?

Royal Oak Way South - Solar Array has a recorded installed capacity of 1.66 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Royal Oak Way South - Solar Array?

REPD records the operator as Cummins Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Royal Oak Way South - Solar Array approved and built?

The application was submitted on 2022-02-22. Permission was granted on 2022-05-24, 3 months later. The site became operational on 2023-10-01, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10790.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council