Novarly ParcelRenewable sites

Renewable sitesKeltneyburn Hydro

Keltneyburn Hydro

Keltneyburn Hydro is an operational 2 MW hydro scheme in Perth and Kinross, generating since 1 May 2010. Planning permission was granted on 24 September 2008, 46 months after submission. Operator of record: Keltneyburn Hydro Ltd.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 May 2010
Small Hydro
Technology
Keltneyburn Hydro Ltd
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted22 November 2004
Permission granted24 September 2008
46 months after submission
Operational1 May 2010
19 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Perth and Kinross: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Keltneyburn Hydro’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
32.27.9 km
Large Hydro · Operational
4010.4 km
Small Hydro · Operational
1.210.7 km
Small Hydro · Operational
1.411.4 km
Small Hydro · Operational
1.111.6 km
Small Hydro · Operational
212.7 km

How big is Keltneyburn Hydro?

Keltneyburn Hydro has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Keltneyburn Hydro?

REPD records the operator as Keltneyburn Hydro Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Keltneyburn Hydro approved and built?

The application was submitted on 22 November 2004. Permission was granted on 24 September 2008, 46 months later. The site became operational on 1 May 2010, 19 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 504.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode