Renewable sites › Calliachar
Calliachar
Calliachar is an operational 32.2 MW onshore wind farm in Perth and Kinross, generating since 30 September 2013. Planning permission was granted on 11 September 2007, 43 months after submission. Operator of record: Scottish and Southern Energy (SSE).
Planning and build timeline
| Application submitted | 16 February 2004 |
| Permission granted | 11 September 2007 43 months after submission |
| Operational | 30 September 2013 73 months after consent |
Screening a site of your own?
Perth and Kinross approves 48% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Calliachar’s recorded coordinate — swap in your own postcode or coordinates.
Perth and Kinross’s record on onshore wind
Perth and Kinross has decided 27 onshore wind schemes and approved 48%, taking a median of 15.2 months. See every onshore wind scheme decision in Perth and Kinross →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Small Hydro · Operational | 1.1 | 3.8 km |
Small Hydro · Operational | 2 | 7.9 km |
Wind Onshore · Operational | 156 | 10.2 km |
Large Hydro · Operational | 15 | 11.5 km |
Large Hydro · Operational | 40 | 12.5 km |
How big is Calliachar?
Calliachar has a recorded installed capacity of 32.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Calliachar?
REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Calliachar approved and built?
The application was submitted on 16 February 2004. Permission was granted on 11 September 2007, 43 months later. The site became operational on 30 September 2013, 73 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4027.
Novarly Parcel · official public data, read properly · parcel.novarly.com