Innerhadden Burn Hydro is an operational 1.4 MW hydro scheme in Perth and Kinross, generating since 1 February 2011. Planning permission was granted on 1 April 2008, 28 months after submission. Operator of record: Innerhadden Hydro.
Planning and build timeline
| Application submitted | 6 December 2005 |
| Permission granted | 1 April 2008 28 months after submission |
| Operational | 1 February 2011 34 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Perth and Kinross: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Innerhadden Burn Hydro’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Small Hydro · Operational | 1.2 | 2.8 km |
Small Hydro · Operational | 1 | 8 km |
Small Hydro · Operational | 2 | 11.4 km |
Small Hydro · Operational | 2 | 12.1 km |
Large Hydro · Operational | 40 | 13.2 km |
How big is Innerhadden Burn Hydro?
Innerhadden Burn Hydro has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Innerhadden Burn Hydro?
REPD records the operator as Innerhadden Hydro. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Innerhadden Burn Hydro approved and built?
The application was submitted on 6 December 2005. Permission was granted on 1 April 2008, 28 months later. The site became operational on 1 February 2011, 34 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 429.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode