Innerhadden Burn Hydro is an operational 1.4 MW hydro scheme in Perth and Kinross, generating since 1 February 2011. Planning permission was granted on 1 April 2008, 28 months after submission. Operator of record: Innerhadden Hydro.

1.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1 February 2011
Small Hydro
Technology
Innerhadden Hydro
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted6 December 2005
Permission granted1 April 2008
28 months after submission
Operational1 February 2011
34 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Perth and Kinross: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Innerhadden Burn Hydro’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Small Hydro · Operational
1.22.8 km
Small Hydro · Operational
18 km
Small Hydro · Operational
211.4 km
Small Hydro · Operational
212.1 km
Large Hydro · Operational
4013.2 km

How big is Innerhadden Burn Hydro?

Innerhadden Burn Hydro has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Innerhadden Burn Hydro?

REPD records the operator as Innerhadden Hydro. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Innerhadden Burn Hydro approved and built?

The application was submitted on 6 December 2005. Permission was granted on 1 April 2008, 28 months later. The site became operational on 1 February 2011, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 429.