Beinn Eagagach Hydro

Beinn Eagagach Hydro is an operational 1.1 MW hydro scheme in Perth and Kinross, generating since 29 January 2016. Planning permission was granted on 24 December 2013, 9 months after submission. Operator of record: Edradynate.

1.1 MW
Capacity
as recorded in REPD
Operational
Status
since 29 January 2016
Small Hydro
Technology
Edradynate
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted15 March 2013
Permission granted24 December 2013
9 months after submission
Operational29 January 2016
25 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Perth and Kinross: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Beinn Eagagach Hydro’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
32.23.8 km
Large Hydro · Operational
157.9 km
Wind Onshore · Operational
1568.8 km
Small Hydro · Operational
211.6 km
Solar Photovoltaics · Operational
0.1613.9 km
Large Hydro · Operational
4014.1 km

How big is Beinn Eagagach Hydro?

Beinn Eagagach Hydro has a recorded installed capacity of 1.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Beinn Eagagach Hydro?

REPD records the operator as Edradynate. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Beinn Eagagach Hydro approved and built?

The application was submitted on 15 March 2013. Permission was granted on 24 December 2013, 9 months later. The site became operational on 29 January 2016, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 453.