Ardtalnaig Hydro Scheme

Ardtalnaig Hydro Scheme is an operational 2 MW hydro scheme in Perth and Kinross, generating since 15 July 2017. Planning permission was granted on 3 December 2012, 5 months after submission. Operator of record: Achomer Energy.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 15 July 2017
Small Hydro
Technology
Achomer Energy
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted12 July 2012
Permission granted3 December 2012
5 months after submission
Operational15 July 2017
55 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Perth and Kinross: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ardtalnaig Hydro Scheme’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Small Hydro · Operational
1.29.4 km
Small Hydro · Operational
1.412.1 km
Small Hydro · Operational
212.7 km
Small Hydro · Operational
113.4 km
Biomass (dedicated) · Operational
5.614.8 km

How big is Ardtalnaig Hydro Scheme?

Ardtalnaig Hydro Scheme has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ardtalnaig Hydro Scheme?

REPD records the operator as Achomer Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ardtalnaig Hydro Scheme approved and built?

The application was submitted on 12 July 2012. Permission was granted on 3 December 2012, 5 months later. The site became operational on 15 July 2017, 55 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 476.