Eckland Lodge Farm is operational in North Northamptonshire with a recorded capacity of 2.9 MW, and has been generating since 2016-12-23.

2.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-12-23
Solar Photovoltaics
Technology
Stuart Howes & Son Ltd
North Northamptonshire
Authority
England

Planning and build timeline

Application submitted2014-10-22
Permission granted2015-07-29
9 months after submission
Operational2016-12-23
17 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Northamptonshire’s record on solar

North Northamptonshire has decided 41 solar farms and approved 98%, taking a median of 2 months. See every solar farm decision in North Northamptonshire

Other built sites within 15 km

SiteMWDistance
Gaultney Solar Park
Solar Photovoltaics · Operational
20.53.2 km
New Albion Wind Farm
Wind Onshore · Operational
14.46 km
Fernbrook AD Plant (Waste AD)
Anaerobic Digestion · Operational
1.57.3 km
Land at Meadow Farm
Solar Photovoltaics · Operational
58.4 km
Kelmarsh Wind Farm (Resubmission)
Wind Onshore · Operational
12.510.1 km
Jacksons Bakery - Solar Panels
Solar Photovoltaics · Under Construction
0.6312.3 km
Pebble Hall Farm - Food Waste AD
Anaerobic Digestion · Operational
412.6 km
Weldon Phase 1 and 2
Landfill Gas · Operational
414 km

How big is Eckland Lodge Farm?

Eckland Lodge Farm has a recorded installed capacity of 2.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Eckland Lodge Farm?

REPD records the operator as Stuart Howes & Son Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Eckland Lodge Farm approved and built?

The application was submitted on 2014-10-22. Permission was granted on 2015-07-29, 9 months later. The site became operational on 2016-12-23, 17 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4705.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council