Novarly ParcelRenewable sites

Renewable sitesIron Mountain Building

Iron Mountain Building

Iron Mountain Building is operational in West Lothian with a recorded capacity of 0.3 MW, and has been generating since 2020-03-01.

0.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2020-03-01
Solar Photovoltaics
Technology
Iron Mountain
West Lothian
Authority
Scotland

Planning and build timeline

Application submitted2019-02-21
Permission granted2019-04-02
1 months after submission
Operational2020-03-01
11 months after consent

West Lothian’s record on solar

West Lothian has decided 16 solar farms and approved 94%, taking a median of 2.2 months. See every solar farm decision in West Lothian

Other built sites within 15 km

SiteMWDistance
Broxburn
Battery · Operational
204 km
Claylands Road
Solar Photovoltaics · Operational
0.27.1 km
Kaimes Landfill Site
Landfill Gas · Operational
2.48.4 km
Aldi Distribution Centre
Solar Photovoltaics · Operational
1.39 km
Pearie Law Wind Farm
Wind Onshore · Operational
19.210.8 km
Harburnhead Wind Farm
Wind Onshore · Operational
51.711.8 km
Pates Hill
Wind Onshore · Operational
1412.4 km
Avondale Quarry (Pilot)
Advanced Conversion Technologies · Operational
213.1 km

How big is Iron Mountain Building?

Iron Mountain Building has a recorded installed capacity of 0.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Iron Mountain Building?

REPD records the operator as Iron Mountain. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Iron Mountain Building approved and built?

The application was submitted on 2019-02-21. Permission was granted on 2019-04-02, 1 months later. The site became operational on 2020-03-01, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7259.