Renewable sites › Broxburn
Broxburn
Broxburn is an operational 20 MW battery storage site in West Lothian, generating since 15 September 2018. Planning permission was granted on 25 November 2016, 4 months after submission. Operator of record: Renewable Energy Systems (RES).
Planning and build timeline
| Application submitted | 3 August 2016 |
| Permission granted | 25 November 2016 4 months after submission |
| Operational | 15 September 2018 22 months after consent |
Screening a site of your own?
West Lothian approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Broxburn’s recorded coordinate — swap in your own postcode or coordinates.
West Lothian’s record on battery storage
West Lothian has decided 8 battery storage schemes and approved 100%, taking a median of 3.9 months. See every battery storage scheme decision in West Lothian →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 0.2 | 3.2 km |
Solar Photovoltaics · Operational | 0.3 | 4 km |
Landfill Gas · Operational | 2.4 | 5.4 km |
Solar Photovoltaics · Operational | 0.2 | 11.5 km |
Wind Onshore · Operational | 19.2 | 12.9 km |
Solar Photovoltaics · Operational | 1.3 | 12.9 km |
Wind Onshore · Operational | 51.7 | 13.2 km |
How big is Broxburn?
Broxburn has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Broxburn?
REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Broxburn approved and built?
The application was submitted on 3 August 2016. Permission was granted on 25 November 2016, 4 months later. The site became operational on 15 September 2018, 22 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6910.