Novarly ParcelRenewable sites

Renewable sitesBroxburn

Broxburn

Broxburn is an operational 20 MW battery storage site in West Lothian, generating since 15 September 2018. Planning permission was granted on 25 November 2016, 4 months after submission. Operator of record: Renewable Energy Systems (RES).

20 MW
Capacity
as recorded in REPD
Operational
Status
since 15 September 2018
Battery
Technology
Renewable Energy Systems (RES)
West Lothian
Authority
Scotland

Planning and build timeline

Application submitted3 August 2016
Permission granted25 November 2016
4 months after submission
Operational15 September 2018
22 months after consent

Screening a site of your own?

RedlineUK · £39

West Lothian approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Broxburn’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

West Lothian’s record on battery storage

West Lothian has decided 8 battery storage schemes and approved 100%, taking a median of 3.9 months. See every battery storage scheme decision in West Lothian

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.23.2 km
Solar Photovoltaics · Operational
0.34 km
Landfill Gas · Operational
2.45.4 km
Solar Photovoltaics · Operational
0.211.5 km
Wind Onshore · Operational
19.212.9 km
Solar Photovoltaics · Operational
1.312.9 km
Wind Onshore · Operational
51.713.2 km

How big is Broxburn?

Broxburn has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Broxburn?

REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Broxburn approved and built?

The application was submitted on 3 August 2016. Permission was granted on 25 November 2016, 4 months later. The site became operational on 15 September 2018, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6910.