Novarly ParcelRenewable sites

Renewable sitesHuddlesford Farm

Huddlesford Farm

Huddlesford Farm is operational in Lichfield with a recorded capacity of 1 MW, and has been generating since 2016-04-15.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-04-15
Solar Photovoltaics
Technology
NESF (formerly Green Energy Networks)
Lichfield
Authority
England

Planning and build timeline

Application submitted2014-06-04
Permission granted2014-10-20
5 months after submission
Operational2016-04-15
18 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Lichfield’s record on solar

Lichfield has decided 9 solar farms and approved 100%, taking a median of 5.1 months. See every solar farm decision in Lichfield

Other built sites within 15 km

SiteMWDistance
Park Lane
Solar Photovoltaics · Operational
10.7 km
Blakenhall Park Solar Farm
Solar Photovoltaics · Operational
1.88.8 km
Wilnecote Landfill Site
Landfill Gas · Operational
111 km
Highfields South Landfill Gas
Landfill Gas · Operational
112.8 km
Drakelow Solar Farm
Solar Photovoltaics · Operational
513 km
Drakelow Renewable Energy Centre
Advanced Conversion Technologies · Under Construction
1513 km
Land at Coton Park Colliery
Solar Photovoltaics · Operational
2.514.6 km

How big is Huddlesford Farm?

Huddlesford Farm has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Huddlesford Farm?

REPD records the operator as NESF (formerly Green Energy Networks). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Huddlesford Farm approved and built?

The application was submitted on 2014-06-04. Permission was granted on 2014-10-20, 5 months later. The site became operational on 2016-04-15, 18 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1804.