Renewable sitesLand at Coton Park Colliery

Land at Coton Park Colliery

Land at Coton Park Colliery is an operational 2.5 MW solar farm in South Derbyshire, generating since 21 December 2015. Planning permission was granted on 9 March 2015, 4 months after submission. Operator of record: NESF (formerly Green Energy Networks).

2.5 MW
Capacity
as recorded in REPD
Operational
Status
since 21 December 2015
Solar Photovoltaics
Technology
NESF (formerly Green Energy Networks)
South Derbyshire
Authority
England

Planning and build timeline

Application submitted10 November 2014
Permission granted9 March 2015
4 months after submission
Operational21 December 2015
9 months after consent

Screening a site of your own?

RedlineUK · £39

South Derbyshire approves 67% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land at Coton Park Colliery’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Derbyshire’s record on solar

South Derbyshire has decided 12 solar farms and approved 67%, taking a median of 4.9 months. See every solar farm decision in South Derbyshire

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
1.63.3 km
Solar Photovoltaics · Operational
0.243.7 km
Solar Photovoltaics · Operational
54.2 km
Advanced Conversion Technologies · Under Construction
154.3 km
Solar Photovoltaics · Operational
54.4 km
Solar Photovoltaics · Operational
56.1 km
Solar Photovoltaics · Operational
166.7 km
Solar Photovoltaics · Operational
37.3 km

How big is Land at Coton Park Colliery?

Land at Coton Park Colliery has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land at Coton Park Colliery?

REPD records the operator as NESF (formerly Green Energy Networks). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land at Coton Park Colliery approved and built?

The application was submitted on 10 November 2014. Permission was granted on 9 March 2015, 4 months later. The site became operational on 21 December 2015, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4767.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode