Drakelow Solar Farm is an operational 5 MW solar farm in South Derbyshire, generating since 15 March 2016. Planning permission was granted on 24 June 2015, 3 months after submission. Operator of record: BlackRock.
Planning and build timeline
| Application submitted | 8 April 2015 |
| Permission granted | 24 June 2015 3 months after submission |
| Operational | 15 March 2016 9 months after consent |
Screening a site of your own?
South Derbyshire approves 67% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Drakelow Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Derbyshire’s record on solar
South Derbyshire has decided 12 solar farms and approved 67%, taking a median of 4.9 months. See every solar farm decision in South Derbyshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Advanced Conversion Technologies · Under Construction | 15 | 0.2 km |
Solar Photovoltaics · Operational | 2.5 | 4.2 km |
Landfill Gas · Operational | 1.6 | 4.8 km |
Solar Photovoltaics · Operational | 1.8 | 6.3 km |
Solar Photovoltaics · Operational | 0.24 | 7.3 km |
Solar Photovoltaics · Operational | 18.7 | 7.6 km |
Solar Photovoltaics · Operational | 5 | 8.4 km |
Solar Photovoltaics · Operational | 5 | 9.6 km |
How big is Drakelow Solar Farm?
Drakelow Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Drakelow Solar Farm?
REPD records the operator as BlackRock. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Drakelow Solar Farm approved and built?
The application was submitted on 8 April 2015. Permission was granted on 24 June 2015, 3 months later. The site became operational on 15 March 2016, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5145.