Solar planning in Lichfield

Lichfield has decided 9 solar farms and approved 100% of them, taking a median of 5.1 months to decide. Consented capacity: 203 MW.

100%
Approved
9 granted · 0 refused
5.1 mo
Median decision
UK 2.3 mo
203 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Lichfield compares

Against the 298 UK authorities with 5+ solar decisions, Lichfield sits in the 77th percentile for approval rate (7 points above the England average) and the 6th percentile for speed.

Decisions by year

35Approved — 2 (2014)214Approved — 1 (2021)121Approved — 2 (2022)222Approved — 2 (2023)223Approved — 2 (2024)224
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (11)

SchemeMWStatusDecided
Little Aston Hospital, Little Aston Hall Drive - Solar panels
Little Aston Hospital · 24/00289/PNPV · 1.4 mo to decide
0.2Awaiting Construction2024-05-09
Steel Processing Midlands, Burntwood Business Park - Solar Panels
Steel Processing Midlands Limited · 23/01426/PNPV · 2.1 mo to decide
0.16Awaiting Construction2024-03-08
Highfields Farm, Clifton Lane - Solar Panels
Elgin Energy ESCO Limited · 22/00110/FULM · 17.7 mo to decide
49.9Awaiting Construction2023-07-11
Newell Rubbermaid, Halifax Avenue - Solar Panels
Newell Rubbermaid UK Services Limited · 23/00040/PNPV · 1.7 mo to decide
0.64Awaiting Construction2023-05-03
Black Flatts Solar Farm
Opdenergy UK 2 Limited · 21/01620/FULM · 7.4 mo to decide
49.9Awaiting Construction2022-05-10
Haunton Solar Farm
Stark Energy · 20/01245/FULM · 16.3 mo to decide
49.9Awaiting Construction2022-04-07
Colton Mill Farm & Cawarden Springs Farm - Solar Panels
Spring Dev 07 Limited · 21/00359/FULM · 9.3 mo to decide
49.9Awaiting Construction2021-11-01
Rawlett Community Sports College
Academies Enterprise Trust · 21/00396/PNC
0.19Application Withdrawn2021-04-15
Parchfields Farm
Solstice Renewables · 15/00834/FULM · 3 mo to decide
1.7Abandoned2015-10-19
Park Lane
NESF (formerly Green Energy Networks) · 14/00518/FULM · 5.7 mo to decide
1Operational2014-11-24
Huddlesford Farm
NESF (formerly Green Energy Networks) · 14/00513/FULM · 4.5 mo to decide
1Operational2014-10-20

Does Lichfield approve solar farms?

Yes — of the 9 solar farms Lichfield has decided, 100% were approved (9 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Lichfield?

The median time from application to decision is 5.1 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Lichfield consented?

203 MW has been consented across 9 approved schemes. There are no applications currently awaiting a decision.

Other technologies in Lichfield

Battery storage in LichfieldOnshore wind in Lichfield

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.