Renewable sites › Pure Malt Products AD
Pure Malt Products AD
Pure Malt Products AD is an operational 1.5 MW anaerobic digestion plant in East Lothian, generating since 1 January 2016. Planning permission was granted on 20 December 2013, 2 months after submission. Operator of record: Pure Malt Products Limited.
Planning and build timeline
| Application submitted | 30 October 2013 |
| Permission granted | 20 December 2013 2 months after submission |
| Operational | 1 January 2016 24 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in East Lothian: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Pure Malt Products AD’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 0.2 | 7.2 km |
Wind Onshore · Operational | 4.8 | 13.8 km |
Wind Onshore · Operational | 144 | 14.9 km |
Wind Onshore · Operational | 20.7 | 14.9 km |
How big is Pure Malt Products AD?
Pure Malt Products AD has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pure Malt Products AD?
REPD records the operator as Pure Malt Products Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pure Malt Products AD approved and built?
The application was submitted on 30 October 2013. Permission was granted on 20 December 2013, 2 months later. The site became operational on 1 January 2016, 24 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 333.
Novarly Parcel · official public data, read properly · parcel.novarly.com