Renewable sites › Holly Farm Solar Park
Holly Farm Solar Park
Holly Farm Solar Park is operational in Dorset with a recorded capacity of 5 MW, and has been generating since 2017-03-31.
Planning and build timeline
| Application submitted | 2015-07-29 |
| Permission granted | 2015-12-18 5 months after submission |
| Operational | 2017-03-31 15 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Nutrient-neutrality catchment — Poole Harbour SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Dorset’s record on solar
Dorset has decided 97 solar farms and approved 95%, taking a median of 3.7 months. See every solar farm decision in Dorset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Crossways Pit Solar Farm Solar Photovoltaics · Operational | 5 | 1.4 km |
Land at East Farm Solar Photovoltaics · Operational | 5 | 1.6 km |
Galton Manor Solar Park Solar Photovoltaics · Operational | 5 | 2.1 km |
Woolbridge Solar Park Solar Photovoltaics · Operational | 5 | 6.6 km |
Dorchesters Corn Exchange - Solar Panels & Biomass Boiler Solar Photovoltaics · Under Construction | — | 9 km |
Dorchesters Corn Exchange - Solar Panels & Biomass Boiler Biomass (dedicated) · Under Construction | — | 9 km |
Stokeford Farm Solar Photovoltaics · Operational | 28.5 | 9.8 km |
Trigon Solar Farm Solar Photovoltaics · Operational | 7 | 10.4 km |
How big is Holly Farm Solar Park?
Holly Farm Solar Park has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Holly Farm Solar Park?
REPD records the operator as British Solar Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Holly Farm Solar Park approved and built?
The application was submitted on 2015-07-29. Permission was granted on 2015-12-18, 5 months later. The site became operational on 2017-03-31, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5632.
Novarly Parcel · official public data, read properly · parcel.novarly.com