Renewable sitesStantway Solar Farm

Stantway Solar Farm

Stantway Solar Farm is an operational 5 MW solar farm in Forest of Dean, generating since 29 March 2014. Planning permission was granted on 13 April 2011, 3 months after submission. Operator of record: Private Developer.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 29 March 2014
Solar Photovoltaics
Technology
Private Developer
Forest of Dean
Authority
England

Planning and build timeline

Application submitted12 January 2011
Permission granted13 April 2011
3 months after submission
Operational29 March 2014
36 months after consent

Screening a site of your own?

RedlineUK · £39

Forest of Dean approves 76% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Stantway Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Forest of Dean’s record on solar

Forest of Dean has decided 25 solar farms and approved 76%, taking a median of 3.1 months. See every solar farm decision in Forest of Dean

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.55.4 km
Solar Photovoltaics · Operational
1.47.8 km
EfW Incineration · Operational
14.58.2 km
Biomass (dedicated) · Operational
2.18.2 km
Solar Photovoltaics · Operational
8.5 km
Solar Photovoltaics · Operational
28.59.9 km
Battery · Operational
10.3 km
Solar Photovoltaics · Operational
49.910.3 km

How big is Stantway Solar Farm?

Stantway Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stantway Solar Farm?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stantway Solar Farm approved and built?

The application was submitted on 12 January 2011. Permission was granted on 13 April 2011, 3 months later. The site became operational on 29 March 2014, 36 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2063.