Novarly ParcelRenewable sites

Renewable sitesStantway Solar Farm

Stantway Solar Farm

Stantway Solar Farm is operational in Forest of Dean with a recorded capacity of 5 MW, and has been generating since 2014-03-29.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-29
Solar Photovoltaics
Technology
Private Developer
Forest of Dean
Authority
England

Planning and build timeline

Application submitted2011-01-12
Permission granted2011-04-13
3 months after submission
Operational2014-03-29
36 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Forest of Dean’s record on solar

Forest of Dean has decided 25 solar farms and approved 76%, taking a median of 3.1 months. See every solar farm decision in Forest of Dean

Other built sites within 15 km

SiteMWDistance
Leeways
Solar Photovoltaics · Operational
0.55.4 km
Vantage Point
Solar Photovoltaics · Operational
1.47.8 km
Javelin Park EfW
EfW Incineration · Operational
14.58.2 km
Markley Group (Premiere Kitckens) Biomass
Biomass (dedicated) · Operational
2.18.2 km
Mobile Telephone Exchange (MTX) - Solar Panels
Solar Photovoltaics · Operational
8.5 km
Hillhouse Farm
Solar Photovoltaics · Operational
28.59.9 km
Highleadon - Solar Arrays & Battery Storage
Battery · Operational
10.3 km
Highleadon - Solar Arrays & Battery Storage
Solar Photovoltaics · Operational
49.910.3 km

How big is Stantway Solar Farm?

Stantway Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stantway Solar Farm?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stantway Solar Farm approved and built?

The application was submitted on 2011-01-12. Permission was granted on 2011-04-13, 3 months later. The site became operational on 2014-03-29, 36 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2063.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council