Javelin Park EfW
Javelin Park EfW is an operational 14.5 MW energy-from-waste plant in Stroud, generating since 24 October 2019. Planning permission was granted on 6 January 2015, 34 months after submission. Operator of record: Urbaser Balfour Beatty.
Planning and build timeline
| Application submitted | 5 March 2012 |
| Permission granted | 6 January 2015 34 months after submission |
| Operational | 24 October 2019 58 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Stroud: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Javelin Park EfW’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Biomass (dedicated) · Operational | 2.1 | 2.1 km |
Solar Photovoltaics · Operational | 0.8 | 4.4 km |
Solar Photovoltaics · Operational | — | 4.5 km |
Solar Photovoltaics · Operational | 28.5 | 8 km |
Solar Photovoltaics · Operational | 5 | 8.2 km |
Solar Photovoltaics · Operational | 2.2 | 9.6 km |
Solar Photovoltaics · Operational | 0.5 | 9.7 km |
Solar Photovoltaics · Under Construction | 1 | 10.2 km |
How big is Javelin Park EfW?
Javelin Park EfW has a recorded installed capacity of 14.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Javelin Park EfW?
REPD records the operator as Urbaser Balfour Beatty. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Javelin Park EfW approved and built?
The application was submitted on 5 March 2012. Permission was granted on 6 January 2015, 34 months later. The site became operational on 24 October 2019, 58 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 998.