Renewable sites › Javelin Park EfW
Javelin Park EfW
Javelin Park EfW is operational in Stroud with a recorded capacity of 14.5 MW, and has been generating since 2019-10-24.
Planning and build timeline
| Application submitted | 2012-03-05 |
| Permission granted | 2015-01-06 34 months after submission |
| Operational | 2019-10-24 58 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Markley Group (Premiere Kitckens) Biomass Biomass (dedicated) · Operational | 2.1 | 2.1 km |
Renishaw PLC Factory Solar Photovoltaics · Operational | 0.8 | 4.4 km |
Mobile Telephone Exchange (MTX) - Solar Panels Solar Photovoltaics · Operational | — | 4.5 km |
Hillhouse Farm Solar Photovoltaics · Operational | 28.5 | 8 km |
Stantway Solar Farm Solar Photovoltaics · Operational | 5 | 8.2 km |
Land at Box Road Solar Photovoltaics · Operational | 2.2 | 9.6 km |
Leeways Solar Photovoltaics · Operational | 0.5 | 9.7 km |
Plant 1, G-Tekt Europe Manufacturing Limited -Roof Mounted Solar Panels Solar Photovoltaics · Under Construction | 1 | 10.2 km |
How big is Javelin Park EfW?
Javelin Park EfW has a recorded installed capacity of 14.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Javelin Park EfW?
REPD records the operator as Urbaser Balfour Beatty. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Javelin Park EfW approved and built?
The application was submitted on 2012-03-05. Permission was granted on 2015-01-06, 34 months later. The site became operational on 2019-10-24, 58 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 998.