Renewable sites › St Fergus Renewable Energy Park
St Fergus Renewable Energy Park
St Fergus Renewable Energy Park is under construction in Aberdeenshire with a recorded capacity of 3 MW.
Planning and build timeline
| Application submitted | 2019-12-03 |
| Permission granted | 2021-07-21 20 months after submission |
| Operational | not recorded |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
St Fergus Renewable Energy Park Battery · Under Construction | — | 0 km |
St Fergus Renewable Energy Park Solar Photovoltaics · Under Construction | 5 | 0 km |
Bruxiehall Farm Solar Photovoltaics · Under Construction | 2 | 1.9 km |
Land at Overside and Greenwellheads Farms Wind Onshore · Operational | 9.2 | 3.9 km |
St Fergus Moss Wind Farm Wind Onshore · Operational | 6 | 4.2 km |
Bilbo Solar Farm Energy Storage Battery · Under Construction | 40 | 5 km |
Bilbo Solar Farm Solar Photovoltaics · Under Construction | 36.6 | 5 km |
Hywind 2 Battery · Operational | 1 | 6.5 km |
How big is St Fergus Renewable Energy Park?
St Fergus Renewable Energy Park has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates St Fergus Renewable Energy Park?
REPD records the operator as Ednie Farms. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was St Fergus Renewable Energy Park approved and built?
The application was submitted on 2019-12-03. Permission was granted on 2021-07-21, 20 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7595.