Harvie Card Way - Solar panels is an operational 1.97 MW solar farm in Milton Keynes, generating since 1 December 2022. Planning permission was granted on 1 October 2021, 3 months after submission. Operator of record: Zestec Asset Management.
Planning and build timeline
| Application submitted | 18 June 2021 |
| Permission granted | 1 October 2021 3 months after submission |
| Operational | 1 December 2022 14 months after consent |
Screening a site of your own?
Milton Keynes approves 91% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Harvie Card Way - Solar panels’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Milton Keynes’s record on solar
Milton Keynes has decided 46 solar farms and approved 91%, taking a median of 1.8 months. See every solar farm decision in Milton Keynes →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | — | 2.3 km |
Solar Photovoltaics · Operational | 0.88 | 3.4 km |
Solar Photovoltaics · Operational | 0.44 | 3.6 km |
Solar Photovoltaics · Operational | 1 | 4.2 km |
Biomass (dedicated) · Operational | 16 | 4.5 km |
Landfill Gas · Operational | 11 | 4.9 km |
Landfill Gas · Operational | 11 | 5 km |
Solar Photovoltaics · Under Construction | 0.26 | 5.5 km |
How big is Harvie Card Way - Solar panels?
Harvie Card Way - Solar panels has a recorded installed capacity of 1.97 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Harvie Card Way - Solar panels?
REPD records the operator as Zestec Asset Management. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Harvie Card Way - Solar panels approved and built?
The application was submitted on 18 June 2021. Permission was granted on 1 October 2021, 3 months later. The site became operational on 1 December 2022, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9253.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode