Harvie Card Way - Solar panels is operational in Milton Keynes with a recorded capacity of 1.97 MW, and has been generating since 2022-12-01.

1.97 MW
Capacity
as recorded in REPD
Operational
Status
since 2022-12-01
Solar Photovoltaics
Technology
Zestec Asset Management
Milton Keynes
Authority
England

Planning and build timeline

Application submitted2021-06-18
Permission granted2021-10-01
3 months after submission
Operational2022-12-01
14 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Milton Keynes’s record on solar

Milton Keynes has decided 46 solar farms and approved 91%, taking a median of 1.8 months. See every solar farm decision in Milton Keynes

Other built sites within 15 km

SiteMWDistance
Blum Uk - Solar Panels
Solar Photovoltaics · Operational
2.3 km
University Way, Cranfield - Solar Array
Solar Photovoltaics · Operational
0.883.4 km
Cranfield University - Solar Farm
Solar Photovoltaics · Operational
0.443.6 km
Cranfield Airfield
Solar Photovoltaics · Operational
14.2 km
Goosey Lodge Industrial Estate
Biomass (dedicated) · Operational
164.5 km
Brogborough Phase III
Landfill Gas · Operational
114.9 km
Brogborough Phase IV
Landfill Gas · Operational
115 km
Caldecote Farm - Storage & Distribution Unit
Solar Photovoltaics · Under Construction
0.265.5 km

How big is Harvie Card Way - Solar panels?

Harvie Card Way - Solar panels has a recorded installed capacity of 1.97 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Harvie Card Way - Solar panels?

REPD records the operator as Zestec Asset Management. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Harvie Card Way - Solar panels approved and built?

The application was submitted on 2021-06-18. Permission was granted on 2021-10-01, 3 months later. The site became operational on 2022-12-01, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9253.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council