Renewable sites › Halstead Renewable Power Project (Waste AD)
Halstead Renewable Power Project (Waste AD)
Halstead Renewable Power Project (Waste AD) is operational in Braintree with a recorded capacity of 2 MW, and has been generating since 2014-07-01.
Planning and build timeline
| Application submitted | 2010-07-16 |
| Permission granted | 2010-08-20 1 months after submission |
| Operational | 2014-07-01 46 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Kentishes Solar Farm Solar Photovoltaics · Operational | 5 | 5.5 km |
Gosfield Airfield Solar Photovoltaics · Operational | 12.6 | 5.6 km |
Periwinkle Hall - Links Solar photovoltaic farm & Battery storage Battery · Operational | — | 8.9 km |
Periwinkle Hall - Links Solar photovoltaic farm & Battery storage Solar Photovoltaics · Operational | 35 | 8.9 km |
Braintree Road, Cressing - Battery Storage Battery · Under Construction | 57 | 9.4 km |
Wren Power and Pulp (Rivenhall Airfield) EfW Incineration · Under Construction | 49.8 | 9.9 km |
Wren Power and Pulp (Rivenhall Airfield) Anaerobic Digestion · Under Construction | 1.8 | 9.9 km |
Cressing Solar Farm (Phase 1) Solar Photovoltaics · Operational | 5 | 11.9 km |
How big is Halstead Renewable Power Project (Waste AD)?
Halstead Renewable Power Project (Waste AD) has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Halstead Renewable Power Project (Waste AD)?
REPD records the operator as Biogen (formerly Tamar Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Halstead Renewable Power Project (Waste AD) approved and built?
The application was submitted on 2010-07-16. Permission was granted on 2010-08-20, 1 months later. The site became operational on 2014-07-01, 46 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 313.