Renewable sitesWren Power and Pulp (Rivenhall Airfield)

Wren Power and Pulp (Rivenhall Airfield)

Wren Power and Pulp (Rivenhall Airfield) is a 1.8 MW anaerobic digestion plant under construction in Braintree. Planning permission was granted on 2 March 2010, 18 months after submission. Operator of record: Gent Fairhead Environmental Services.

1.8 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Anaerobic Digestion
Technology
Gent Fairhead Environmental Services
Braintree
Authority
England

Planning and build timeline

Application submitted8 September 2008
Permission granted2 March 2010
18 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Braintree: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Wren Power and Pulp (Rivenhall Airfield)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
EfW Incineration · Under Construction
49.80 km
Solar Photovoltaics · Operational
352 km
Battery · Operational
2 km
Solar Photovoltaics · Operational
53.5 km
Solar Photovoltaics · Operational
0.194.9 km
Battery · Under Construction
575.6 km
Solar Photovoltaics · Operational
2.85.9 km
Solar Photovoltaics · Operational
12.25.9 km

How big is Wren Power and Pulp (Rivenhall Airfield)?

Wren Power and Pulp (Rivenhall Airfield) has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wren Power and Pulp (Rivenhall Airfield)?

REPD records the operator as Gent Fairhead Environmental Services. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wren Power and Pulp (Rivenhall Airfield) approved and built?

The application was submitted on 8 September 2008. Permission was granted on 2 March 2010, 18 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 352.