Renewable sites › Wren Power and Pulp (Rivenhall Airfield)
Wren Power and Pulp (Rivenhall Airfield)
Wren Power and Pulp (Rivenhall Airfield) is under construction in Braintree with a recorded capacity of 1.8 MW.
Planning and build timeline
| Application submitted | 2008-09-08 |
| Permission granted | 2010-03-02 18 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wren Power and Pulp (Rivenhall Airfield) EfW Incineration · Under Construction | 49.8 | 0 km |
Periwinkle Hall - Links Solar photovoltaic farm & Battery storage Solar Photovoltaics · Operational | 35 | 2 km |
Periwinkle Hall - Links Solar photovoltaic farm & Battery storage Battery · Operational | — | 2 km |
Cressing Solar Farm (Phase 1) Solar Photovoltaics · Operational | 5 | 3.5 km |
Morrisons Witham - Solar Pv Panels Solar Photovoltaics · Operational | 0.19 | 4.9 km |
Braintree Road, Cressing - Battery Storage Battery · Under Construction | 57 | 5.6 km |
Highfields Farm (Colchester) Solar Photovoltaics · Operational | 12.2 | 5.9 km |
Highfields Farm (Braintree) Solar Photovoltaics · Operational | 2.8 | 5.9 km |
How big is Wren Power and Pulp (Rivenhall Airfield)?
Wren Power and Pulp (Rivenhall Airfield) has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wren Power and Pulp (Rivenhall Airfield)?
REPD records the operator as Gent Fairhead Environmental Services. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wren Power and Pulp (Rivenhall Airfield) approved and built?
The application was submitted on 2008-09-08. Permission was granted on 2010-03-02, 18 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 352.