Halsary Wind Farm is an operational 34 MW onshore wind farm in Highland, generating since 31 March 2021. Planning permission was granted on 19 September 2013, 46 months after submission. Operator of record: Scottish Power Renewables.

34 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2021
Wind Onshore
Technology
Scottish Power Renewables
Highland
Authority
Scotland

Planning and build timeline

Application submitted9 November 2009
Permission granted19 September 2013
46 months after submission
Operational31 March 2021
90 months after consent

Screening a site of your own?

RedlineUK · £39

Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Halsary Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
26.71.5 km
Wind Onshore · Operational
102.1 km
Wind Onshore · Operational
5010.4 km
Wind Onshore · Operational
3.911.5 km
Wind Onshore · Under Construction
72.611.6 km
Wind Onshore · Operational
1012.8 km
Wind Onshore · Under Construction
3613.2 km
Wind Onshore · Operational
18.513.4 km

How big is Halsary Wind Farm?

Halsary Wind Farm has a recorded installed capacity of 34 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Halsary Wind Farm?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Halsary Wind Farm approved and built?

The application was submitted on 9 November 2009. Permission was granted on 19 September 2013, 46 months later. The site became operational on 31 March 2021, 90 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4636.