Renewable sites › Wathegar wind farm
Wathegar wind farm
Wathegar wind farm is operational in Highland with a recorded capacity of 10 MW, and has been generating since 2013-03-31.
Planning and build timeline
| Application submitted | 2010-02-09 |
| Permission granted | 2010-05-21 3 months after submission |
| Operational | 2013-03-31 34 months after consent |
Highland’s record on onshore wind
Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wathegar 2 Wind Farm Wind Onshore · Operational | 18.5 | 0.7 km |
Achairn Wind Onshore · Operational | 6.2 | 1.4 km |
Bilbster Wind Farm Wind Onshore · Operational | 3.9 | 1.8 km |
Camster II Wind Onshore · Under Construction | 36 | 2.4 km |
Camster Wind Onshore · Operational | 50 | 4.3 km |
Pulteney Distillery Biomass (dedicated) · Operational | 3.5 | 8.2 km |
Causeymire Wind Onshore · Operational | 48.3 | 8.2 km |
Burn of Whilk Wind Onshore · Operational | 22.5 | 9.3 km |
How big is Wathegar wind farm?
Wathegar wind farm has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wathegar wind farm?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wathegar wind farm approved and built?
The application was submitted on 2010-02-09. Permission was granted on 2010-05-21, 3 months later. The site became operational on 2013-03-31, 34 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3757.