Renewable sites › Wathegar 2 Wind Farm
Wathegar 2 Wind Farm
Wathegar 2 Wind Farm is an operational 18.5 MW onshore wind farm in Highland, generating since 15 September 2017. Planning permission was granted on 23 March 2012, 5 months after submission. Operator of record: BayWa r.e..
Planning and build timeline
| Application submitted | 10 October 2011 |
| Permission granted | 23 March 2012 5 months after submission |
| Operational | 15 September 2017 66 months after consent |
Screening a site of your own?
Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Wathegar 2 Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Highland’s record on onshore wind
Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 10 | 0.7 km |
Wind Onshore · Operational | 6.2 | 0.9 km |
Wind Onshore · Under Construction | 36 | 2 km |
Wind Onshore · Operational | 3.9 | 2.5 km |
Wind Onshore · Operational | 50 | 4.4 km |
Biomass (dedicated) · Operational | 3.5 | 7.6 km |
Wind Onshore · Operational | 48.3 | 7.7 km |
Wind Onshore · Operational | 22.5 | 8.8 km |
How big is Wathegar 2 Wind Farm?
Wathegar 2 Wind Farm has a recorded installed capacity of 18.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wathegar 2 Wind Farm?
REPD records the operator as BayWa r.e.. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wathegar 2 Wind Farm approved and built?
The application was submitted on 10 October 2011. Permission was granted on 23 March 2012, 5 months later. The site became operational on 15 September 2017, 66 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4425.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode