Renewable sitesCamster

Camster

Camster is an operational 50 MW onshore wind farm in Scotland, generating since 9 February 2013. Planning permission was granted on 13 January 2009, 48 months after submission. Operator of record: E.ON UK.

50 MW
Capacity
as recorded in REPD
Operational
Status
since 9 February 2013
Wind Onshore
Technology
E.ON UK
National
Authority
Scotland

Planning and build timeline

Application submitted5 January 2005
Permission granted13 January 2009
48 months after submission
Operational9 February 2013
49 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Camster’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Under Construction
363.1 km
Wind Onshore · Operational
104.3 km
Wind Onshore · Operational
18.54.4 km
Wind Onshore · Operational
3.94.7 km
Wind Onshore · Operational
6.25.3 km
Wind Onshore · Operational
22.57 km
Wind Onshore · Under Construction
72.67.7 km
Wind Onshore · Operational
26.79.3 km

How big is Camster?

Camster has a recorded installed capacity of 50 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Camster?

REPD records the operator as E.ON UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Camster approved and built?

The application was submitted on 5 January 2005. Permission was granted on 13 January 2009, 48 months later. The site became operational on 9 February 2013, 49 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4006.