Camster
Camster is operational in Scottish Government (S36) with a recorded capacity of 50 MW, and has been generating since 2013-02-09.
Planning and build timeline
| Application submitted | 2005-01-05 |
| Permission granted | 2009-01-13 48 months after submission |
| Operational | 2013-02-09 49 months after consent |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Camster II Wind Onshore · Under Construction | 36 | 3.1 km |
Wathegar wind farm Wind Onshore · Operational | 10 | 4.3 km |
Wathegar 2 Wind Farm Wind Onshore · Operational | 18.5 | 4.4 km |
Bilbster Wind Farm Wind Onshore · Operational | 3.9 | 4.7 km |
Achairn Wind Onshore · Operational | 6.2 | 5.3 km |
Burn of Whilk Wind Onshore · Operational | 22.5 | 7 km |
Golticlay Wind Farm Wind Onshore · Under Construction | 72.6 | 7.7 km |
Bad a Cheo Wind Farm Wind Onshore · Operational | 26.7 | 9.3 km |
How big is Camster?
Camster has a recorded installed capacity of 50 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Camster?
REPD records the operator as E.ON UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Camster approved and built?
The application was submitted on 2005-01-05. Permission was granted on 2009-01-13, 48 months later. The site became operational on 2013-02-09, 49 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4006.