Renewable sitesCamster

Camster

Camster is operational in Scottish Government (S36) with a recorded capacity of 50 MW, and has been generating since 2013-02-09.

50 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-02-09
Wind Onshore
Technology
E.ON UK
Scottish Government (S36)
Authority
Scotland

Planning and build timeline

Application submitted2005-01-05
Permission granted2009-01-13
48 months after submission
Operational2013-02-09
49 months after consent

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Camster II
Wind Onshore · Under Construction
363.1 km
Wathegar wind farm
Wind Onshore · Operational
104.3 km
Wathegar 2 Wind Farm
Wind Onshore · Operational
18.54.4 km
Bilbster Wind Farm
Wind Onshore · Operational
3.94.7 km
Achairn
Wind Onshore · Operational
6.25.3 km
Burn of Whilk
Wind Onshore · Operational
22.57 km
Golticlay Wind Farm
Wind Onshore · Under Construction
72.67.7 km
Bad a Cheo Wind Farm
Wind Onshore · Operational
26.79.3 km

How big is Camster?

Camster has a recorded installed capacity of 50 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Camster?

REPD records the operator as E.ON UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Camster approved and built?

The application was submitted on 2005-01-05. Permission was granted on 2009-01-13, 48 months later. The site became operational on 2013-02-09, 49 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4006.