Bilbster Wind Farm
Bilbster Wind Farm is operational in Highland with a recorded capacity of 3.9 MW, and has been generating since 2008-02-01.
Planning and build timeline
| Application submitted | 2004-01-23 |
| Permission granted | not recorded |
| Operational | 2008-02-01 |
Highland’s record on onshore wind
Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wathegar wind farm Wind Onshore · Operational | 10 | 1.8 km |
Wathegar 2 Wind Farm Wind Onshore · Operational | 18.5 | 2.5 km |
Achairn Wind Onshore · Operational | 6.2 | 3 km |
Camster II Wind Onshore · Under Construction | 36 | 3.9 km |
Camster Wind Onshore · Operational | 50 | 4.7 km |
Causeymire Wind Onshore · Operational | 48.3 | 9.6 km |
Pulteney Distillery Biomass (dedicated) · Operational | 3.5 | 9.7 km |
Burn of Whilk Wind Onshore · Operational | 22.5 | 10.6 km |
How big is Bilbster Wind Farm?
Bilbster Wind Farm has a recorded installed capacity of 3.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bilbster Wind Farm?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bilbster Wind Farm approved and built?
The application was submitted on 2004-01-23. REPD does not record a grant date. The site became operational on 2008-02-01.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3207.