Renewable sitesBad a Cheo Wind Farm

Bad a Cheo Wind Farm

Bad a Cheo Wind Farm is operational in Highland with a recorded capacity of 26.7 MW, and has been generating since 2019-05-01.

26.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2019-05-01
Wind Onshore
Technology
Innogy
Highland
Authority
Scotland

Planning and build timeline

Application submitted2012-07-25
Permission granted2014-05-06
21 months after submission
Operational2019-05-01
60 months after consent

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Halsary Wind Farm
Wind Onshore · Operational
341.5 km
Achlachan Wind Farm
Wind Onshore · Operational
103.5 km
Camster
Wind Onshore · Operational
509.3 km
Golticlay Wind Farm
Wind Onshore · Under Construction
72.610.1 km
Bilbster Wind Farm
Wind Onshore · Operational
3.910.9 km
Wathegar wind farm
Wind Onshore · Operational
1012.1 km
Camster II
Wind Onshore · Under Construction
3612.2 km
Wathegar 2 Wind Farm
Wind Onshore · Operational
18.512.6 km

How big is Bad a Cheo Wind Farm?

Bad a Cheo Wind Farm has a recorded installed capacity of 26.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bad a Cheo Wind Farm?

REPD records the operator as Innogy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bad a Cheo Wind Farm approved and built?

The application was submitted on 2012-07-25. Permission was granted on 2014-05-06, 21 months later. The site became operational on 2019-05-01, 60 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4646.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council