Greenoakhill

Greenoakhill is an operational 3.9 MW landfill gas site in Glasgow City, generating since 1 June 2000. Planning permission was granted on 30 June 1999, 1 months after submission. Operator of record: Graveson Energy Management.

3.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 June 2000
Landfill Gas
Technology
Graveson Energy Management
Glasgow City
Authority
Scotland

Planning and build timeline

Application submitted1 June 1999
Permission granted30 June 1999
1 months after submission
Operational1 June 2000
11 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Glasgow City: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Greenoakhill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
0.866.1 km
Large Hydro · Under Construction
6.1 km
Solar Photovoltaics · Operational
0.246.6 km
Landfill Gas · Operational
7.46.6 km
Small Hydro · Operational
6.9 km
Wind Onshore · Operational
37 km
Anaerobic Digestion · Operational
57.1 km
Advanced Conversion Technologies · Operational
107.1 km

How big is Greenoakhill?

Greenoakhill has a recorded installed capacity of 3.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Greenoakhill?

REPD records the operator as Graveson Energy Management. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Greenoakhill approved and built?

The application was submitted on 1 June 1999. Permission was granted on 30 June 1999, 1 months later. The site became operational on 1 June 2000, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 689.