Renewable sites › Gawnsmoss Cluster
Gawnsmoss Cluster
Gawnsmoss Cluster is an operational 2.4 MW onshore wind farm in Aberdeenshire, generating since 27 March 2017. Planning permission was granted on 11 March 2015, 29 months after submission. Operator of record: Farm Energy Consulting.
Planning and build timeline
| Application submitted | 10 October 2012 |
| Permission granted | 11 March 2015 29 months after submission |
| Operational | 27 March 2017 25 months after consent |
Screening a site of your own?
Aberdeenshire approves 69% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Gawnsmoss Cluster’s recorded coordinate — swap in your own postcode or coordinates.
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 2.3 | 2 km |
Wind Onshore · Operational | 4.6 | 2 km |
Wind Onshore · Operational | 6.9 | 3.5 km |
Wind Onshore · Operational | 2.3 | 4.6 km |
Wind Onshore · Operational | 2.3 | 4.9 km |
Wind Onshore · Operational | 2.4 | 5 km |
Wind Onshore · Operational | 16.7 | 5 km |
Wind Onshore · Operational | 4.7 | 5.6 km |
How big is Gawnsmoss Cluster?
Gawnsmoss Cluster has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Gawnsmoss Cluster?
REPD records the operator as Farm Energy Consulting. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gawnsmoss Cluster approved and built?
The application was submitted on 10 October 2012. Permission was granted on 11 March 2015, 29 months later. The site became operational on 27 March 2017, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4892.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode