Renewable sites › Gawnsmoss Cluster
Gawnsmoss Cluster
Gawnsmoss Cluster is operational in Aberdeenshire with a recorded capacity of 2.4 MW, and has been generating since 2017-03-27.
Planning and build timeline
| Application submitted | 2012-10-10 |
| Permission granted | 2015-03-11 29 months after submission |
| Operational | 2017-03-27 25 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Strath of Brydock Wind Onshore · Operational | 4.6 | 2 km |
Strath of Brydock - Extension Wind Onshore · Operational | 2.3 | 2 km |
Deuchries Wind Onshore · Operational | 6.9 | 3.5 km |
Mornflake Oats Wind Turbine Wind Onshore · Operational | 2.3 | 4.6 km |
Boyndie Airfield Extension Wind Onshore · Operational | 2.3 | 4.9 km |
Auchinderran Wind Farm Wind Onshore · Operational | 2.4 | 5 km |
Boyndie Airfield Wind Onshore · Operational | 16.7 | 5 km |
Deuchries Windfarm (extension) (Bradley 2) Wind Onshore · Operational | 4.7 | 5.6 km |
How big is Gawnsmoss Cluster?
Gawnsmoss Cluster has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Gawnsmoss Cluster?
REPD records the operator as Farm Energy Consulting. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gawnsmoss Cluster approved and built?
The application was submitted on 2012-10-10. Permission was granted on 2015-03-11, 29 months later. The site became operational on 2017-03-27, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4892.
Novarly Parcel · official public data, read properly · parcel.novarly.com