Renewable sitesDeuchries

Deuchries

Deuchries is operational in Aberdeenshire with a recorded capacity of 6.9 MW, and has been generating since 2017-12-15.

6.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-12-15
Wind Onshore
Technology
Force 9 Energy / Catamount Energy/ Green Cat
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted2012-11-13
Permission granted2014-04-17
17 months after submission
Operational2017-12-15
44 months after consent

Aberdeenshire’s record on onshore wind

Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Deuchries Windfarm (extension) (Bradley 2)
Wind Onshore · Operational
4.72.1 km
Auchinderran Wind Farm
Wind Onshore · Operational
2.42.1 km
Gawnsmoss Cluster
Wind Onshore · Operational
2.43.5 km
Strath of Brydock - Extension
Wind Onshore · Operational
2.34.5 km
Strath of Brydock
Wind Onshore · Operational
4.64.5 km
Muirake
Wind Onshore · Operational
4.66.9 km
Mornflake Oats Wind Turbine
Wind Onshore · Operational
2.37.9 km
Boyndie Airfield Extension
Wind Onshore · Operational
2.38.1 km

How big is Deuchries?

Deuchries has a recorded installed capacity of 6.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Deuchries?

REPD records the operator as Force 9 Energy / Catamount Energy/ Green Cat. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Deuchries approved and built?

The application was submitted on 2012-11-13. Permission was granted on 2014-04-17, 17 months later. The site became operational on 2017-12-15, 44 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4360.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council