Boyndie Airfield

Boyndie Airfield is operational in Aberdeenshire with a recorded capacity of 16.7 MW, and has been generating since 2006-02-01.

16.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2006-02-01
Wind Onshore
Technology
RDC Scotland Ltd/ Falck Renewables
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted2003-06-24
Permission granted2004-07-23
13 months after submission
Operational2006-02-01
18 months after consent

Aberdeenshire’s record on onshore wind

Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Mornflake Oats Wind Turbine
Wind Onshore · Operational
2.30.7 km
Boyndie Airfield Extension
Wind Onshore · Operational
2.30.9 km
Gawnsmoss Cluster
Wind Onshore · Operational
2.45 km
Strath of Brydock - Extension
Wind Onshore · Operational
2.35.6 km
Strath of Brydock
Wind Onshore · Operational
4.65.6 km
Muirake
Wind Onshore · Operational
4.67.9 km
Deuchries
Wind Onshore · Operational
6.98.4 km
Auchinderran Wind Farm
Wind Onshore · Operational
2.49.4 km

How big is Boyndie Airfield?

Boyndie Airfield has a recorded installed capacity of 16.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Boyndie Airfield?

REPD records the operator as RDC Scotland Ltd/ Falck Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Boyndie Airfield approved and built?

The application was submitted on 2003-06-24. Permission was granted on 2004-07-23, 13 months later. The site became operational on 2006-02-01, 18 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4671.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council