Renewable sites › Boyndie Airfield
Boyndie Airfield
Boyndie Airfield is operational in Aberdeenshire with a recorded capacity of 16.7 MW, and has been generating since 2006-02-01.
Planning and build timeline
| Application submitted | 2003-06-24 |
| Permission granted | 2004-07-23 13 months after submission |
| Operational | 2006-02-01 18 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Mornflake Oats Wind Turbine Wind Onshore · Operational | 2.3 | 0.7 km |
Boyndie Airfield Extension Wind Onshore · Operational | 2.3 | 0.9 km |
Gawnsmoss Cluster Wind Onshore · Operational | 2.4 | 5 km |
Strath of Brydock - Extension Wind Onshore · Operational | 2.3 | 5.6 km |
Strath of Brydock Wind Onshore · Operational | 4.6 | 5.6 km |
Muirake Wind Onshore · Operational | 4.6 | 7.9 km |
Deuchries Wind Onshore · Operational | 6.9 | 8.4 km |
Auchinderran Wind Farm Wind Onshore · Operational | 2.4 | 9.4 km |
How big is Boyndie Airfield?
Boyndie Airfield has a recorded installed capacity of 16.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Boyndie Airfield?
REPD records the operator as RDC Scotland Ltd/ Falck Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Boyndie Airfield approved and built?
The application was submitted on 2003-06-24. Permission was granted on 2004-07-23, 13 months later. The site became operational on 2006-02-01, 18 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4671.