Novarly ParcelRenewable sites

Renewable sitesGawcott Fields Farm

Gawcott Fields Farm

Gawcott Fields Farm is operational in Buckinghamshire with a recorded capacity of 9.2 MW, and has been generating since 2015-12-15.

9.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-12-15
Solar Photovoltaics
Technology
Harper Solar Ltd
Buckinghamshire
Authority
England

Planning and build timeline

Application submitted2014-07-29
Permission granted2014-10-28
3 months after submission
Operational2015-12-15
14 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Buckinghamshire’s record on solar

Buckinghamshire has decided 59 solar farms and approved 90%, taking a median of 3 months. See every solar farm decision in Buckinghamshire

Other built sites within 15 km

SiteMWDistance
Buckingham Tesco Superstore
Solar Photovoltaics · Operational
0.21.6 km
Land at Thornborough Grounds
Solar Photovoltaics · Operational
55.8 km
Fox Covert Solar Farm
Solar Photovoltaics · Operational
227.7 km
Shelswell Park Solar Farm
Solar Photovoltaics · Operational
57.8 km
Fox Covert Solar Farm
Battery · Operational
7.9 km
Greatmoor EfW
EfW Incineration · Operational
228.3 km
Turweston Solar Farm
Solar Photovoltaics · Operational
16.78.5 km
Mount Mill Farm
Solar Photovoltaics · Operational
129.5 km

How big is Gawcott Fields Farm?

Gawcott Fields Farm has a recorded installed capacity of 9.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Gawcott Fields Farm?

REPD records the operator as Harper Solar Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Gawcott Fields Farm approved and built?

The application was submitted on 2014-07-29. Permission was granted on 2014-10-28, 3 months later. The site became operational on 2015-12-15, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2227.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council