Fox Covert Solar Farm is operational in Buckinghamshire with a recorded capacity of 22 MW, and has been generating since 2023-10-12.

22 MW
Capacity
as recorded in REPD
Operational
Status
since 2023-10-12
Solar Photovoltaics
Technology
Low Carbon
Buckinghamshire
Authority
England

Planning and build timeline

Application submitted2020-08-03
Permission granted2021-06-01
10 months after submission
Operational2023-10-12
28 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Buckinghamshire’s record on solar

Buckinghamshire has decided 59 solar farms and approved 90%, taking a median of 3 months. See every solar farm decision in Buckinghamshire

Other built sites within 15 km

SiteMWDistance
Fox Covert Solar Farm
Battery · Operational
0.2 km
Land at Thornborough Grounds
Solar Photovoltaics · Operational
55.4 km
Buckingham Tesco Superstore
Solar Photovoltaics · Operational
0.26.3 km
Land At Potash Farm
Solar Photovoltaics · Operational
76.5 km
Stony Energy Storage Facility
Battery · Operational
79.96.6 km
Gawcott Fields Farm
Solar Photovoltaics · Operational
9.27.7 km
Mount Mill Farm
Solar Photovoltaics · Operational
128.6 km
Greatmoor EfW
EfW Incineration · Operational
228.6 km

How big is Fox Covert Solar Farm?

Fox Covert Solar Farm has a recorded installed capacity of 22 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Fox Covert Solar Farm?

REPD records the operator as Low Carbon. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Fox Covert Solar Farm approved and built?

The application was submitted on 2020-08-03. Permission was granted on 2021-06-01, 10 months later. The site became operational on 2023-10-12, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7958.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council