Week Farm Solar Park is operational in Torridge with a recorded capacity of 3.3 MW, and has been generating since 2014-03-28.

3.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-28
Solar Photovoltaics
Technology
Unknown
Torridge
Authority
England

Planning and build timeline

Application submitted2013-04-15
Permission granted2013-07-30
3 months after submission
Operational2014-03-28
8 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Torridge’s record on solar

Torridge has decided 28 solar farms and approved 96%, taking a median of 3.6 months. See every solar farm decision in Torridge

Other built sites within 15 km

SiteMWDistance
Darracott Moor
Wind Onshore · Operational
2.62.2 km
Deep Moor Landfill Site
Solar Photovoltaics · Operational
22.5 km
Deep Moor Gas to Energy
Landfill Gas · Operational
22.7 km
Knockworthy Farm
Solar Photovoltaics · Operational
3.53.7 km
Cleave Farm Solar Park
Solar Photovoltaics · Operational
4.76 km
Gammaton Moor Solar farm
Solar Photovoltaics · Under Construction
326.3 km
Beaford Brook Solar Park
Solar Photovoltaics · Operational
5.26.6 km
Chubb Road - Solar Photovoltaic
Solar Photovoltaics · Operational
0.158.4 km

How big is Week Farm Solar Park?

Week Farm Solar Park has a recorded installed capacity of 3.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Week Farm Solar Park?

REPD records the operator as Unknown. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Week Farm Solar Park approved and built?

The application was submitted on 2013-04-15. Permission was granted on 2013-07-30, 3 months later. The site became operational on 2014-03-28, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1659.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council