French Farm

French Farm is operational in Peterborough with a recorded capacity of 4 MW, and has been generating since 2016-11-24.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-11-24
Wind Onshore
Technology
REG Windpower (previously Cornwall Light and Power)
Peterborough
Authority
England

Planning and build timeline

Application submitted2008-11-06
Permission granted2010-09-10
22 months after submission
Operational2016-11-24
74 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Decoy Farm
Solar Photovoltaics · Operational
54.3 km
Decoy Farm (Farm AD)
Anaerobic Digestion · Operational
1.84.3 km
Wryde Croft
Wind Onshore · Operational
265.4 km
Dogsthorpe South Landfill Site 2
Landfill Gas · Operational
1.410.5 km
Dogsthorpe South Landfill Site
Landfill Gas · Operational
1.910.5 km
Deeping St Nicholas Wind Farm
Wind Onshore · Operational
16.411.2 km
Peterborough EfW
EfW Incineration · Operational
7.312 km
Spalding
Biomass (dedicated) · Operational
14.512.5 km

How big is French Farm?

French Farm has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates French Farm?

REPD records the operator as REG Windpower (previously Cornwall Light and Power). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was French Farm approved and built?

The application was submitted on 2008-11-06. Permission was granted on 2010-09-10, 22 months later. The site became operational on 2016-11-24, 74 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4637.