Renewable sites › Wryde Croft
Wryde Croft
Wryde Croft is an operational 26 MW onshore wind farm in Peterborough, generating since 20 February 2016. Planning permission was granted on 1 April 2010, 45 months after submission. Operator of record: Renewable Energy Systems (RES).
Planning and build timeline
| Application submitted | 1 July 2006 |
| Permission granted | 1 April 2010 45 months after submission |
| Operational | 20 February 2016 71 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Peterborough: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Wryde Croft’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 4 | 5.4 km |
Solar Photovoltaics · Operational | 0.2 | 9 km |
Solar Photovoltaics · Operational | 5 | 9.2 km |
Anaerobic Digestion · Operational | 1.8 | 9.3 km |
Wind Onshore · Operational | 16 | 10 km |
Anaerobic Digestion · Operational | 1.5 | 10.4 km |
Wind Onshore · Operational | 14 | 10.9 km |
Wind Onshore · Operational | 2 | 11.3 km |
How big is Wryde Croft?
Wryde Croft has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wryde Croft?
REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wryde Croft approved and built?
The application was submitted on 1 July 2006. Permission was granted on 1 April 2010, 45 months later. The site became operational on 20 February 2016, 71 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4248.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode