Novarly ParcelRenewable sites

Renewable sitesWryde Croft

Wryde Croft

Wryde Croft is operational in Peterborough with a recorded capacity of 26 MW, and has been generating since 2016-02-20.

26 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-02-20
Wind Onshore
Technology
Renewable Energy Systems (RES)
Peterborough
Authority
England

Planning and build timeline

Application submitted2006-07-01
Permission granted2010-04-01
45 months after submission
Operational2016-02-20
71 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
French Farm
Wind Onshore · Operational
45.4 km
Volmary Site
Solar Photovoltaics · Operational
0.29 km
Decoy Farm
Solar Photovoltaics · Operational
59.2 km
Decoy Farm (Farm AD)
Anaerobic Digestion · Operational
1.89.3 km
Coldham
Wind Onshore · Operational
1610 km
Fenmarc Fenland AD Plant (Waste AD)
Anaerobic Digestion · Operational
1.510.4 km
Coldham Hall
Wind Onshore · Operational
1410.9 km
Long Hill Road
Wind Onshore · Operational
211.3 km

How big is Wryde Croft?

Wryde Croft has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wryde Croft?

REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wryde Croft approved and built?

The application was submitted on 2006-07-01. Permission was granted on 2010-04-01, 45 months later. The site became operational on 2016-02-20, 71 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4248.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council