Novarly ParcelRenewable sites

Renewable sitesDecoy Farm (Farm AD)

Decoy Farm (Farm AD)

Decoy Farm (Farm AD) is an operational 1.8 MW anaerobic digestion plant in South Holland, generating since 1 July 2016. Planning permission was granted on 21 February 2011, 2 months after submission. Operator of record: Organic Recycling.

1.8 MW
Capacity
as recorded in REPD
Operational
Status
since 1 July 2016
Anaerobic Digestion
Technology
Organic Recycling
South Holland
Authority
England

Planning and build timeline

Application submitted22 December 2010
Permission granted21 February 2011
2 months after submission
Operational1 July 2016
64 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in South Holland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Decoy Farm (Farm AD)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.3 km
Wind Onshore · Operational
44.3 km
Wind Onshore · Operational
16.47.2 km
Biomass (dedicated) · Operational
14.58.5 km
Wind Onshore · Operational
269.3 km
Landfill Gas · Operational
1.412 km
Landfill Gas · Operational
1.912.1 km
Solar Photovoltaics · Operational
12.713.8 km

How big is Decoy Farm (Farm AD)?

Decoy Farm (Farm AD) has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Decoy Farm (Farm AD)?

REPD records the operator as Organic Recycling. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Decoy Farm (Farm AD) approved and built?

The application was submitted on 22 December 2010. Permission was granted on 21 February 2011, 2 months later. The site became operational on 1 July 2016, 64 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 367.