Dogsthorpe South Landfill Site

Dogsthorpe South Landfill Site is operational in Peterborough with a recorded capacity of 1.9 MW, and has been generating since 1995-09-01.

1.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1995-09-01
Landfill Gas
Technology
Waste Recycling Group
Peterborough
Authority
England

Planning and build timeline

Application submitted1994-02-17
Permission granted1995-05-10
15 months after submission
Operational1995-09-01
4 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Dogsthorpe South Landfill Site 2
Landfill Gas · Operational
1.40.1 km
Peterborough EfW
EfW Incineration · Operational
7.33.1 km
McCain Foods AD Plant (AD)
Anaerobic Digestion · Operational
15.7 km
Whittlesey
Wind Onshore · Operational
95.9 km
Black Bush Farm
Solar Photovoltaics · Operational
2.77.7 km
French Farm
Wind Onshore · Operational
410.5 km
Glass Moor
Wind Onshore · Operational
1612 km
Glass moor Extension
Wind Onshore · Operational
1212 km

How big is Dogsthorpe South Landfill Site?

Dogsthorpe South Landfill Site has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dogsthorpe South Landfill Site?

REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dogsthorpe South Landfill Site approved and built?

The application was submitted on 1994-02-17. Permission was granted on 1995-05-10, 15 months later. The site became operational on 1995-09-01, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 525.