Renewable sites › Dogsthorpe South Landfill Site 2
Dogsthorpe South Landfill Site 2
Dogsthorpe South Landfill Site 2 is operational in Peterborough with a recorded capacity of 1.4 MW, and has been generating since 2005-08-01.
Planning and build timeline
| Application submitted | 2003-01-09 |
| Permission granted | 2004-05-24 16 months after submission |
| Operational | 2005-08-01 14 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Dogsthorpe South Landfill Site Landfill Gas · Operational | 1.9 | 0.1 km |
Peterborough EfW EfW Incineration · Operational | 7.3 | 3.1 km |
McCain Foods AD Plant (AD) Anaerobic Digestion · Operational | 1 | 5.7 km |
Whittlesey Wind Onshore · Operational | 9 | 5.9 km |
Black Bush Farm Solar Photovoltaics · Operational | 2.7 | 7.7 km |
French Farm Wind Onshore · Operational | 4 | 10.5 km |
Decoy Farm (Farm AD) Anaerobic Digestion · Operational | 1.8 | 12 km |
Glass Moor Wind Onshore · Operational | 16 | 12 km |
How big is Dogsthorpe South Landfill Site 2?
Dogsthorpe South Landfill Site 2 has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dogsthorpe South Landfill Site 2?
REPD records the operator as Shanks Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dogsthorpe South Landfill Site 2 approved and built?
The application was submitted on 2003-01-09. Permission was granted on 2004-05-24, 16 months later. The site became operational on 2005-08-01, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 638.