Fforch Nest Wind Farm pt2

Fforch Nest Wind Farm pt2 is operational in Bridgend with a recorded capacity of 17.5 MW, and has been generating since 2013-05-24.

17.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-05-24
Wind Onshore
Technology
Pennant Walters
Bridgend
Authority
Wales

Planning and build timeline

Application submitted2006-03-31
Permission granted2011-05-04
61 months after submission
Operational2013-05-24
25 months after consent

Bridgend’s record on onshore wind

Bridgend has decided 10 onshore wind schemes and approved 60%, taking a median of 9.3 months. See every onshore wind scheme decision in Bridgend

Other built sites within 15 km

SiteMWDistance
Fforch Nest Wind Farm pt1
Wind Onshore · Operational
100.5 km
Pant y wal
Wind Onshore · Operational
250.9 km
Pant y wal extension
Wind Onshore · Operational
202.8 km
Former Nant-y-Gwyddon Landfill Site
Wind Onshore · Under Construction
1.53.3 km
Taff Ely Wind Farm
Wind Onshore · Operational
94.7 km
Brynpica Landfill Site
Landfill Gas · Operational
2.75.8 km
Penrhys Wind Farm/Ferndale Power Factory
Wind Onshore · Operational
6.45.9 km
Mynydd Portref Wind Farm extension
Wind Onshore · Operational
126.1 km

How big is Fforch Nest Wind Farm pt2?

Fforch Nest Wind Farm pt2 has a recorded installed capacity of 17.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Fforch Nest Wind Farm pt2?

REPD records the operator as Pennant Walters. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Fforch Nest Wind Farm pt2 approved and built?

The application was submitted on 2006-03-31. Permission was granted on 2011-05-04, 61 months later. The site became operational on 2013-05-24, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3932.