Novarly ParcelRenewable sites

Renewable sitesFforch Nest Wind Farm pt2

Fforch Nest Wind Farm pt2

Fforch Nest Wind Farm pt2 is an operational 17.5 MW onshore wind farm in Bridgend, generating since 24 May 2013. Planning permission was granted on 4 May 2011, 61 months after submission. Operator of record: Pennant Walters.

17.5 MW
Capacity
as recorded in REPD
Operational
Status
since 24 May 2013
Wind Onshore
Technology
Pennant Walters
Bridgend
Authority
Wales

Planning and build timeline

Application submitted31 March 2006
Permission granted4 May 2011
61 months after submission
Operational24 May 2013
25 months after consent

Screening a site of your own?

RedlineUK · £39

Bridgend approves 60% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Fforch Nest Wind Farm pt2’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Bridgend’s record on onshore wind

Bridgend has decided 10 onshore wind schemes and approved 60%, taking a median of 9.3 months. See every onshore wind scheme decision in Bridgend

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
100.5 km
Wind Onshore · Operational
250.9 km
Wind Onshore · Operational
202.8 km
Wind Onshore · Under Construction
1.53.3 km
Wind Onshore · Operational
94.7 km
Landfill Gas · Operational
2.75.8 km
Wind Onshore · Operational
6.45.9 km
Wind Onshore · Operational
126.1 km

How big is Fforch Nest Wind Farm pt2?

Fforch Nest Wind Farm pt2 has a recorded installed capacity of 17.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Fforch Nest Wind Farm pt2?

REPD records the operator as Pennant Walters. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Fforch Nest Wind Farm pt2 approved and built?

The application was submitted on 31 March 2006. Permission was granted on 4 May 2011, 61 months later. The site became operational on 24 May 2013, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3932.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode