Renewable sites › Fforch Nest Wind Farm pt1
Fforch Nest Wind Farm pt1
Fforch Nest Wind Farm pt1 is operational in Rhondda Cynon Taf with a recorded capacity of 10 MW, and has been generating since 2013-05-24.
Planning and build timeline
| Application submitted | 2006-08-31 |
| Permission granted | 2011-05-04 56 months after submission |
| Operational | 2013-05-24 25 months after consent |
Rhondda Cynon Taf’s record on onshore wind
Rhondda Cynon Taf has decided 13 onshore wind schemes and approved 92%, taking a median of 23.1 months. See every onshore wind scheme decision in Rhondda Cynon Taf →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Fforch Nest Wind Farm pt2 Wind Onshore · Operational | 17.5 | 0.5 km |
Pant y wal Wind Onshore · Operational | 25 | 0.7 km |
Former Nant-y-Gwyddon Landfill Site Wind Onshore · Under Construction | 1.5 | 2.8 km |
Pant y wal extension Wind Onshore · Operational | 20 | 3.3 km |
Taff Ely Wind Farm Wind Onshore · Operational | 9 | 5.1 km |
Brynpica Landfill Site Landfill Gas · Operational | 2.7 | 5.3 km |
Penrhys Wind Farm/Ferndale Power Factory Wind Onshore · Operational | 6.4 | 5.4 km |
Mynydd Portref Wind Farm extension Wind Onshore · Operational | 12 | 6.4 km |
How big is Fforch Nest Wind Farm pt1?
Fforch Nest Wind Farm pt1 has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Fforch Nest Wind Farm pt1?
REPD records the operator as Pennant Walters. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Fforch Nest Wind Farm pt1 approved and built?
The application was submitted on 2006-08-31. Permission was granted on 2011-05-04, 56 months later. The site became operational on 2013-05-24, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3956.